Residents protesting a planned desalination plant in Mazotos parked their cars at the construction site in an attempt to stop crews from building the roads that will serve the facility.
The protesters say the project went ahead without consultation with the wider community. They are asking to meet with President Nikos Christodoulides to raise their concerns directly.
The proposed plant in the Petountas area has drawn opposition for nearly a year. In a recent majority vote, the Mazotos Community Council decided to open talks with the government about what the village could receive in compensation for hosting the facility. With work on the access roads underway, protesters are still pressing for a say on the project itself.
The mobile plant is designed to produce 40,000 cubic meters of water a day, equivalent to 40 million liters. The project is expected to cost more than €92 million and is scheduled for completion in 2027.