Apostolos Tomaras
Contracts worth between $1.3 billion and $1.8 billion have been signed for the Cronos field and its commercial development, once again bringing the Republic of Cyprus’ energy program into focus.
The decision by the field’s operator, Italy’s Eni, marks a milestone in Cyprus’ ambition to become a producer of natural gas after a journey spanning at least 20 years. But the significance of the contracts signed in Nicosia last month goes beyond the commercial development of one field in Cyprus’ exclusive economic zone, or EEZ, which now appears close to being realized.
With plans advancing to develop the Pegasus and Glaucus fields, the U.S. energy giant is openly signalling interest in expanding beyond Block 10.
Cronos entering production is expected to have a positive impact on the other fields discovered in the EEZ, putting pressure on their operators to speed up the steps needed to bring them into production. Nicosia is also expected to seize the momentum created by Cronos and try to open a new round of offshore licensing, both to strengthen the EEZ’s energy potential and to secure a stronger presence for international energy companies.
One possible contender is U.S. company ExxonMobil. It could become the second company to commercially develop fields in Cyprus’ EEZ, with the Pegasus and Glaucus discoveries estimated to hold about 4 trillion cubic feet of gas. The company is also looking to expand beyond Block 10, which it operates.
The Aphrodite field remains a major obstacle in Cyprus’ energy plans. Discovered in 2011, it was the first find in the EEZ and marked the start of exploration in the area.
A vote of confidence
ExxonMobil’s entry into Cyprus’ EEZ, through the award of Block 10 in 2017, was one of Nicosia’s key successes in building a network of energy partnerships with international giants.
The U.S. company affirmed its confidence in Cyprus’ EEZ even as it cut back projects in other parts of the world. ExxonMobil not only stayed in the region but is now preparing to expand into other offshore blocks.
The government’s intention to launch a new licensing round appears to be supported by interest from companies already operating in the EEZ, as well as other international players with experience in the hydrocarbons industry.
A source familiar with ExxonMobil’s plans told Kathimerini that the company is interested in other blocks in the EEZ and is seriously considering bidding for one in a new licensing round. The blocks that have not yet been licensed and could be offered are Blocks 1, 2, 3, 4, 9 and 13.
Greek energy company HELLENiQ ENERGY is also considering entering the race for a block. It is active in Cyprus’ retail fuel market and in exploration in parts of southern Greece. The company’s chief executive, Andreas Siamisiis, did not rule out a move into Cyprus’ EEZ when asked by Kathimerini.
Moving toward an investment decision
ExxonMobil, which operates Block 10, is advancing plans to commercially develop its two discoveries, Glaucus and Pegasus, which together are estimated to hold about 4 trillion cubic feet of gas. The company signed a declaration of commerciality for the fields this year.
A drilling rig is expected to return to Block 10 by the end of the year to carry out two wells. A company executive told Kathimerini that the results will lead to the submission of a development and production plan, followed by a final investment decision.
A new agreement
Chevron joined the Aphrodite field’s ownership consortium in 2020. A new agreement was finalized in 2025, without changing the previously agreed development model: a floating production unit, or FPU, at the field, with gas exported to Egypt.
The final investment decision is officially expected in 2027. But industry figures have questioned that timeline, arguing that Chevron is deliberately delaying progress and prioritizing the neighboring Leviathan field in Israel’s EEZ, which is larger and expected to generate greater returns.
Those figures believe the operator’s strategy is intended to put pressure on Nicosia to secure better terms for Chevron.
Sixteen years of negotiations
Israel’s claims to part of the Aphrodite field appear to be another factor behind the delay. The disputed area is in Cyprus’ Block 12 and extends into the Ishai field in Israel’s EEZ.
Israeli demands have prevented the negotiations from reaching an agreement. The talks date back to the administration of President Demetris Christofias, when Neoklis Sylikiotis was energy minister. Repeated efforts have failed, and discussions between the two countries have produced no breakthrough.
Sources familiar with the talks told Kathimerini that, faced with the deadlock, the Cypriot side has decided to proceed with developing Aphrodite without an agreement with Israel. That decision has also been incorporated into the revised development and production plan agreed with Chevron, which states that resolving the dispute with Israel is not a precondition for moving ahead.